FPC was selected by Charlotte County and Babcock Ranch to construct a new 3-apparatus bay Fire/EMS station and CCSO District office in the growing community of Babcock Ranch. Both stations were designs of previous prototypes adapted to meet the specific needs of the town. The Master Development Order between Babcock Ranch and Charlotte County required construction of the shells to occur under a separate contract than the interiors. FPC completed the shell construction, paused for 30 days to allow for property conveyance, then completed the interiors as a stand-alone project. This was challenging from an operational perspective in the field as well administratively. FPC successfully coordinated all construction activities between multiple owners, architects, and departments.
Babcock Ranch Public Safety Complex: Fire Station #9 & Ccso District 5 HQ
Project Details
Location:
Babcock Ranch, FL
Year Completed:
2025
Cost:
$13 Million – combined total of 2 contracts between Charlotte County & Babcock Ranch.
Delivery Method:
CM@Risk